That GreenStreets Pedestrian Plaza Outside Punjabi Deli & Grocery Won’t be Ready Until October 2016

Posted on: January 13th, 2016 at 5:00 am by

houston-construction-2

The clusterfuck that is the East Houston Street reconstruction project is a pounding migraine that refuses to abate. Residents in the vicinity have, for years, contended with excess noise, street dust, and traffic bottleneck. But for the Punjabi Deli & Grocery, it’s had a negative effect on customers and bottom line alike.

Three months after presenting updates regarding ongoing infrastructural project, the contractor’s liaison Paul Kidder returned to Community Board 3 last night, but also dragged along the spokesmen from DDC, Con Edison, and Verizon for more detailed info. Unfortunately, the operative word of the night was – unsurprisingly – delay. Not only is the project delayed three years, but the September 2016 completion date previously provided was stretched again by another month. If you’re keeping score at home, that’s easily the third revised end date in recent memory. Blame more of the “utility interference” that contractors encounter each time the roadway is torn asunder (i.e. encountering issues with different agency wiring that needs attention).

1st-sidewalk-1

As previously reported, the GreenStreets pedestrian plaza outside Punjabi Deli (once part of East First Street) is complete. Yet the city agencies refuse to remove the staging area there, and make good on the promise to finally plant greenery and park benches. The excuse given was that the project wouldn’t be finished until October 2016 (one month past initial delayed end date), and they didn’t want to potentially damage the new plantings. This angered District Manager Susan Stetzer, who reminded the team that the community was promised a springtime planting, and that there’s no reason why the 100%-complete area can’t be given back to the public.

The multimillion-dollar capital works project began on the west side of Manhattan over a decade ago and reached the Bowery around June 2010. This was the start of Phase II, initially slated to last three years. Not surprisingly, the estimate was twice revised – first to December 2015, and most recently to September 2016

The project has gotten so out of hand that even now City Hall is finally paying attention. Each of the representatives present last night was summoned and given the directive to expedite.

houston-construction-1

Other updates:

  • Some of the road restoration should commence by springtime – paving roadbed, establishing medians, and planting the beds. (Before GreenStreets??)
  • Con Edison is responsible for ripping up the roadway at First Avenue to upgrade the 30″ gas mains. They’re taking advantage of the open project, but won’t finish until the end of next month. DDC can’t continue until the utility completes its job.
  • You may have noticed that the Second Avenue intersection was also excavated to install more piping. That’s delayed due to the utility interference.
  • Member David Crane voiced concern over whether the plumbing of these planting beds (i.e. “concrete bathtubs”) will still drain the water. There is worry that overflows would flood the business that are below grade.
  • The community is sick of being held hostage by multiple staging areas clogging up the nearby blocks. The DDC was supposed to have addressed the situation back in October, but obviously didn’t.
  • The M15 and M21 bus stop east of Chrystie Street won’t return until the construction period concludes next October. The concrete roadbed, curb, and sidewalk must first be rebuilt.

Community Board 3 ultimately voted and carried a resolution that memorialized the concerns.

Recent Stories

‘Jones LES’ Luxury Rental Development Sells for $61M

Exactly one year after it hit the market, the luxury rental complex at 331 East Houston, dubbed “Jones LES,” is under new ownership. The development changed hands for an unbelievable $61 million. Gili Haberberg, an investor who runs Arkar Inc., will shell out $61 million for the 67,600-square-foot elevator building situated between Attorney and Ridge streets. According to […]

AG Introduces Bill that Would Hold Slumlords Criminally Accountable for Tenant Harassment

There is finally a bit of momentum in combating slumlords who have made an apparent cottage industry out of tenant harassment. Offenders such as Steve Croman, Dean Galasso, and Samy Mahfar are finally being held accountable, even if the punishments don’t necessarily fit the bill. Yesterday, state attorney general Eric Schneiderman introduced a new bill that […]

Football Cafe Returns After Month-long Forced Closure from Building Renovations

Birds & Bubbles was not alone. Alleged negligent renovation work at 100 Forsyth Street also played a role in the brief shutter of address mate Football Cafe. The coffee shop had been temporarily closed for the past month without much indication as to why. Unspecified “renovations” was the reason provided via computer printout. We’ve since confirmed, […]

The Pier 35 Screenwall Installation this Week is the Most Activity Here in 3 Years

It’s actually happening. Clean the crust from you eyes. Work has finally resumed at Pier 35 on the Lower East Side waterfront. Steel elements for the problematic screenwall – the shield for the neighboring pier and cause for much of the delay – began arriving this week, about three months later than promised. Crews were […]

Cashing in on the Bowery Graffiti Wall with ‘Limited Edition’ Prints

Last week, Goldman Properties announced that art fans could “own a piece” of the famous Bowery Graffiti Wall. “For the first time in history,” the copy read in all-caps, people could purchase limited edition prints of the PichiAvo mural (“Urbanmythology”) currently holding court. Cashing in on the wall. Seventy-five 47” x 15” archival color prints, […]