That GreenStreets Pedestrian Plaza Outside Punjabi Deli & Grocery Won’t be Ready Until October 2016

Posted on: January 13th, 2016 at 5:00 am by

houston-construction-2

The clusterfuck that is the East Houston Street reconstruction project is a pounding migraine that refuses to abate. Residents in the vicinity have, for years, contended with excess noise, street dust, and traffic bottleneck. But for the Punjabi Deli & Grocery, it’s had a negative effect on customers and bottom line alike.

Three months after presenting updates regarding ongoing infrastructural project, the contractor’s liaison Paul Kidder returned to Community Board 3 last night, but also dragged along the spokesmen from DDC, Con Edison, and Verizon for more detailed info. Unfortunately, the operative word of the night was – unsurprisingly – delay. Not only is the project delayed three years, but the September 2016 completion date previously provided was stretched again by another month. If you’re keeping score at home, that’s easily the third revised end date in recent memory. Blame more of the “utility interference” that contractors encounter each time the roadway is torn asunder (i.e. encountering issues with different agency wiring that needs attention).

1st-sidewalk-1

As previously reported, the GreenStreets pedestrian plaza outside Punjabi Deli (once part of East First Street) is complete. Yet the city agencies refuse to remove the staging area there, and make good on the promise to finally plant greenery and park benches. The excuse given was that the project wouldn’t be finished until October 2016 (one month past initial delayed end date), and they didn’t want to potentially damage the new plantings. This angered District Manager Susan Stetzer, who reminded the team that the community was promised a springtime planting, and that there’s no reason why the 100%-complete area can’t be given back to the public.

The multimillion-dollar capital works project began on the west side of Manhattan over a decade ago and reached the Bowery around June 2010. This was the start of Phase II, initially slated to last three years. Not surprisingly, the estimate was twice revised – first to December 2015, and most recently to September 2016

The project has gotten so out of hand that even now City Hall is finally paying attention. Each of the representatives present last night was summoned and given the directive to expedite.

houston-construction-1

Other updates:

  • Some of the road restoration should commence by springtime – paving roadbed, establishing medians, and planting the beds. (Before GreenStreets??)
  • Con Edison is responsible for ripping up the roadway at First Avenue to upgrade the 30″ gas mains. They’re taking advantage of the open project, but won’t finish until the end of next month. DDC can’t continue until the utility completes its job.
  • You may have noticed that the Second Avenue intersection was also excavated to install more piping. That’s delayed due to the utility interference.
  • Member David Crane voiced concern over whether the plumbing of these planting beds (i.e. “concrete bathtubs”) will still drain the water. There is worry that overflows would flood the business that are below grade.
  • The community is sick of being held hostage by multiple staging areas clogging up the nearby blocks. The DDC was supposed to have addressed the situation back in October, but obviously didn’t.
  • The M15 and M21 bus stop east of Chrystie Street won’t return until the construction period concludes next October. The concrete roadbed, curb, and sidewalk must first be rebuilt.

Community Board 3 ultimately voted and carried a resolution that memorialized the concerns.

Recent Stories

LES Crepes & Taqueria Wraps Around Hester Street with New Annex

LES Crepes & Taqueria just unveiled its newly improved eat space on Essex Street. Customers are now forced to enter the premises at the corner. No more ordering and waiting for food on the sidewalk. One of the workers explained his pleasure with putting the claustrophobia in the past. By breaking down the wall to […]

How About an Evening ‘Tasting’ at Ray’s Candy Store Tonight?

Now that the summertime (bougie) Restaurant Week has come to a close, time to spend an evening with an Alphabet City classic. Indeed, there is a special “tasting” event later this evening at Ray’s Candy Store. For the accessible ten-spot cover charge, proprietor Ray Alvarez will serve a “5-course meal including selections of Ray’s famous […]

SHUT Skateboards Shutting Down its Orchard Street HQ

Looks like SHUT is shutting its flagship skateshop on the Lower East Side. The store has been part of the retail landscape here for about ten years. And as of last week, there is now a Misrahi Realty leasing sign hanging in the front window. It’s indication enough that more turnover is around the corner. […]

Two-Story Shops at 330-332 Grand Street Sell for $6M, Demolition and Redevelopment Imminent

Back in April, we noticed some unusual activity happening at 330-332 Grand Street. The roll-down gates for all five commercial units were hoisted, and the sidewalk flaps to the cellar opened. This could only mean one thing – imminent changing of the guard. And that’s exactly what happened. According to public records, the holdout two-story […]

Linkin Park’s Chester Bennington Gets a Tribute on Ludlow Street

Late Linkin Park leadman is now memorialized on the Lower East Side. Barely one month after Chester Bennington committed suicide at 41, an unknown fan stuck his image onto the facade of 159 Ludlow Street (aka 101 Stanton). The distinctive photo is itself framed by a television set and stands apart from the collage of […]