That GreenStreets Pedestrian Plaza Outside Punjabi Deli & Grocery Won’t be Ready Until October 2016

Posted on: January 13th, 2016 at 5:00 am by

houston-construction-2

The clusterfuck that is the East Houston Street reconstruction project is a pounding migraine that refuses to abate. Residents in the vicinity have, for years, contended with excess noise, street dust, and traffic bottleneck. But for the Punjabi Deli & Grocery, it’s had a negative effect on customers and bottom line alike.

Three months after presenting updates regarding ongoing infrastructural project, the contractor’s liaison Paul Kidder returned to Community Board 3 last night, but also dragged along the spokesmen from DDC, Con Edison, and Verizon for more detailed info. Unfortunately, the operative word of the night was – unsurprisingly – delay. Not only is the project delayed three years, but the September 2016 completion date previously provided was stretched again by another month. If you’re keeping score at home, that’s easily the third revised end date in recent memory. Blame more of the “utility interference” that contractors encounter each time the roadway is torn asunder (i.e. encountering issues with different agency wiring that needs attention).

1st-sidewalk-1

As previously reported, the GreenStreets pedestrian plaza outside Punjabi Deli (once part of East First Street) is complete. Yet the city agencies refuse to remove the staging area there, and make good on the promise to finally plant greenery and park benches. The excuse given was that the project wouldn’t be finished until October 2016 (one month past initial delayed end date), and they didn’t want to potentially damage the new plantings. This angered District Manager Susan Stetzer, who reminded the team that the community was promised a springtime planting, and that there’s no reason why the 100%-complete area can’t be given back to the public.

The multimillion-dollar capital works project began on the west side of Manhattan over a decade ago and reached the Bowery around June 2010. This was the start of Phase II, initially slated to last three years. Not surprisingly, the estimate was twice revised – first to December 2015, and most recently to September 2016

The project has gotten so out of hand that even now City Hall is finally paying attention. Each of the representatives present last night was summoned and given the directive to expedite.

houston-construction-1

Other updates:

  • Some of the road restoration should commence by springtime – paving roadbed, establishing medians, and planting the beds. (Before GreenStreets??)
  • Con Edison is responsible for ripping up the roadway at First Avenue to upgrade the 30″ gas mains. They’re taking advantage of the open project, but won’t finish until the end of next month. DDC can’t continue until the utility completes its job.
  • You may have noticed that the Second Avenue intersection was also excavated to install more piping. That’s delayed due to the utility interference.
  • Member David Crane voiced concern over whether the plumbing of these planting beds (i.e. “concrete bathtubs”) will still drain the water. There is worry that overflows would flood the business that are below grade.
  • The community is sick of being held hostage by multiple staging areas clogging up the nearby blocks. The DDC was supposed to have addressed the situation back in October, but obviously didn’t.
  • The M15 and M21 bus stop east of Chrystie Street won’t return until the construction period concludes next October. The concrete roadbed, curb, and sidewalk must first be rebuilt.

Community Board 3 ultimately voted and carried a resolution that memorialized the concerns.

Recent Stories

In ‘Wayfinding’ Flub, City Moves Sidewalk Post to the Correct Spot

The Department of Transportation is apparently in need of its own wayfinding in Chinatown. You may have noticed that this WalkNYC installation was previously erected on the wrong spot. The signage first arrived near the southeast corner of Essex and Canal Streets at the end of November. Upon closer inspection, though, the “You are here” […]

Last 2 Parking Lots on Delancey Street Closing in the Next Month for Essex Crossing Towers

For the first time in fifty years – since the notorious “urban renewal” slum clearance of 1967 – the last two parking lots on Delancey Street will soon go under the knife. The parcels are incorporated into the Essex Crossing development, and as such, are ready for their luxury payload. The Lower East Side Partnership […]

Elected Officials Come out Against Redevelopment of Elizabeth Street Garden as Senior Housing

The Department of Housing Preservation and Development awarded the contract last Friday for an affordable housing project atop the Elizabeth Street Garden. All but a death sentence for the open space. The proposed building – developed by Penrose Development – will rise seven stories and carry 121 permanently affordable apartments for seniors. And as if […]

Witnessing the Destruction of Beth Hamedrash Hagadol Synagogue [PHOTOS]

Chisel and drill are fully deployed to dispense with one of the oldest synagogues in New York City. Beth Hamedrash Hagadol – constructed in 1850 and hollowed out by three-alarm fire last May – is being demolished as we speak. Literally brick by brick. Each day, the landmarked 167-year-old house of worship (closed and vacant […]

Elizabeth Street Garden will be Bulldozed and Redeveloped by Penrose Development

Now that election season is over, there is finally movement toward the controversial destruction and redevelopment of the Elizabeth Street Garden. The city will apparently announce today that it’s chosen the developer to carry out this task. The Department of Housing Preservation and Development awarded the contract for the seven-story project to Penrose Development. The […]