That GreenStreets Pedestrian Plaza Outside Punjabi Deli & Grocery Won’t be Ready Until October 2016

Posted on: January 13th, 2016 at 5:00 am by
This image has been archived or removed.

The clusterfuck that is the East Houston Street reconstruction project is a pounding migraine that refuses to abate. Residents in the vicinity have, for years, contended with excess noise, street dust, and traffic bottleneck. But for the Punjabi Deli & Grocery, it’s had a negative effect on customers and bottom line alike.

Three months after presenting updates regarding ongoing infrastructural project, the contractor’s liaison Paul Kidder returned to Community Board 3 last night, but also dragged along the spokesmen from DDC, Con Edison, and Verizon for more detailed info. Unfortunately, the operative word of the night was – unsurprisingly – delay. Not only is the project delayed three years, but the September 2016 completion date previously provided was stretched again by another month. If you’re keeping score at home, that’s easily the third revised end date in recent memory. Blame more of the “utility interference” that contractors encounter each time the roadway is torn asunder (i.e. encountering issues with different agency wiring that needs attention).

This image has been archived or removed.

As previously reported, the GreenStreets pedestrian plaza outside Punjabi Deli (once part of East First Street) is complete. Yet the city agencies refuse to remove the staging area there, and make good on the promise to finally plant greenery and park benches. The excuse given was that the project wouldn’t be finished until October 2016 (one month past initial delayed end date), and they didn’t want to potentially damage the new plantings. This angered District Manager Susan Stetzer, who reminded the team that the community was promised a springtime planting, and that there’s no reason why the 100%-complete area can’t be given back to the public.

The multimillion-dollar capital works project began on the west side of Manhattan over a decade ago and reached the Bowery around June 2010. This was the start of Phase II, initially slated to last three years. Not surprisingly, the estimate was twice revised – first to December 2015, and most recently to September 2016

The project has gotten so out of hand that even now City Hall is finally paying attention. Each of the representatives present last night was summoned and given the directive to expedite.

This image has been archived or removed.

Other updates:

  • Some of the road restoration should commence by springtime – paving roadbed, establishing medians, and planting the beds. (Before GreenStreets??)
  • Con Edison is responsible for ripping up the roadway at First Avenue to upgrade the 30″ gas mains. They’re taking advantage of the open project, but won’t finish until the end of next month. DDC can’t continue until the utility completes its job.
  • You may have noticed that the Second Avenue intersection was also excavated to install more piping. That’s delayed due to the utility interference.
  • Member David Crane voiced concern over whether the plumbing of these planting beds (i.e. “concrete bathtubs”) will still drain the water. There is worry that overflows would flood the business that are below grade.
  • The community is sick of being held hostage by multiple staging areas clogging up the nearby blocks. The DDC was supposed to have addressed the situation back in October, but obviously didn’t.
  • The M15 and M21 bus stop east of Chrystie Street won’t return until the construction period concludes next October. The concrete roadbed, curb, and sidewalk must first be rebuilt.

Community Board 3 ultimately voted and carried a resolution that memorialized the concerns.

Recent Stories

Gigs to See on the Downtown Music Circuit the Month of August

The downtown music scene is approaching pre-pandemic levels, thanks in large part to increased bookings at many bars, restaurants and nightclubs. August looks more promising than any schedule in the past 16 months. Here are some highlights of upcoming shows this month, along with photographs from a few of the more active venues in July. […]

The Double-Decker Dining Shed on East 4th Street that Almost Happened

The dining shed as we know it is moving on up. Literally. Outside the Izakaya NYC on East 4th Street, workers were spotted assembling a double-decker dining shed on Friday morning. Complete with stairs, second floor, and astroturf. With the mezzanine at eye level with the first-floor apartments. By the evening, word was out and […]

Nolita Sommelier Charged with Setting Fire to Downtown Dining Structures

Photo: Forsythia Fire Department brass last week announced charges against a celebrated sommelier for setting fire to downtown dining structures. Caleb Ganzer, sommelier and partner at wine bar La Compagnie des Vins Surnaturels on Centre Street, was arrested and charged with two counts of felony for three instances of arson, including two at outdoor dining […]

Exit through the Ludlow Street Food Court

Exit through the food court. Indeed, the vacant Ludlow Street lot made famous by Banksy over a decade ago is now a mini food court. Under the radar, too. The first day of operations at 159 Ludlow was apparently Friday, including two food trucks, produce vendors, and picnic table seating. One of the vendors is […]

Stringer Punts on East Side Coastal Resilience Contract

For advocates of East River Park, a brief reprieve. City Comptroller, and former mayoral candidate Scott Stringer did not sign the $1.2 billion construction contract with IPC Resiliency Partners that would kickstart city funding for the East Side Coastal Resilience project. It apparently boils down to missing info and the review period having elapsed. “As […]