Delayed and Under-Funded, Pier 42 Esplanade Won’t be Complete until 2020 (at Least)

Posted on: July 14th, 2017 at 5:00 am by

Community leaders at Pier 42, September 2012

Already at least five years on the boards, the project to create public greenspace at Pier 42 is still nowhere near completion. Lack of funding apparently fueled the delays. But there is now some progress to report courtesy of a cash injection.

Three years after last appearing before Community Board 3, spokespeople from the Economic Development Corp. provided an update to the Parks subcommittee last night. The big takeaway is that additional federal funding from the Lower Manhattan Development Corp. helped jumpstart the first phase (costing roughly $14 million).

Indeed, so-called Phase 1A includes asbestos abatement and demolition of the pier shed, which should commence in October and wrap by next summer. Staging area for this job will be in the adjacent parking lot (the business operating there will close the month prior).

The extra money also goes toward two design elements not in the initial master plan – comfort station (aka toilets) and a playground – together comprising Phase 1B seen in the rendering below. The city (with Mathews Nielsen Landscape Architects) is at the very beginning of design duties, so there aren’t many details about the latter, other than the bathrooms will sit on elevated land (above the flood line). This part of the project will also include new plantings, lighting, and site furnishings.

Construction of both is slated to start in July 2018.

Other pertinents:

  • EDC is now responsible for administration and design of the project. Parks Department is maintenance partner.
  • EDC will soon start work on designing the playground and comfort station, with the goal of finalizing the plans by spring 2018.
  • There is not enough funding yet for Phase 2, which would see build-out of the shed replacement and completion of the esplanade.
  • There was concern from the panel about overall safety in accessing the public park, from lack of lighting to speeding cars off the FDR to the dangerous intersection at Montgomery Street.
  • Pier 42 completion date and public opening is pegged at March 2020, over four years after the last prediction.

Community Board 3 approved the plans to add the additional amenities to the project, but asked that the EDC team return in the fall to provide a more robust update.

Updated rendering

Recent Stories

Sounds of the Lower East Side, Circa 1934 [VIDEO]

Back in February, we posted a compelling, decades-old video of life in the Big Apple during 1929. The best part about this original footage was the authentic audio track paired to it. Now, the video editor behind that clip (alias Guy Jones) has struck again with a new video of Lower East Side living in […]

Chinatown Bus Block of East Broadway Welcomes New Pizzeria

The de-facto “bus depot” that is East Broadway between Pike and Rutgers will soon welcome its second pizza joint. The as-yet-unnamed slice spot is to take up residence in the east store of 150 East Broadway, the space previously held by a short-lived barbershop. With this addition alongside the Japanese dessert shop, The Little One, […]

It Took 6 Days to Assemble this Prefab LES Condo Development

Second announced, but first to the finish, 193 Henry Street is considered the first modular housing development on the Lower East Side. And it took less than a week to stack up the building blocks. Brooklyn-based Think! Architecture + Design was quick to point out this week on Instagram that the new seven-story construction was swiftly […]

10-Story ODA Condo Tops out on Chrystie Street

One of two ODA-designed condo towers along Chrystie just reached the top. The construction at 165 Chrystie Street topped out within the last couple weeks, boasting the token visuals of vertical completion. Flags. Not one, two, or three, but four national flags. A veritable United Nations forum with America, Russia, China, and Israel. Reaching this […]

Disarmed: Partner Dispute Leads to Shutter of Suffolk Arms

Suffolk Arms mysteriously shuttered during the first week of April due to “renovations” and “mechanical upgrades.” Sounds convincing … not. Apparently, the closure is related to a dispute between co-owners Giuseppe González and well-regarded bartender Ruben Rodriguez. The former allegedly sought the ouster of the latter this past winter. However, according to a report in […]